November 2017 Update

WE HAVE BROKEN GROUND! We are excited as the work on the first major project is under way. We have broken ground at the new Langston Elementary site. The new Langston campus will be erected on the current Langston campus in the playground area. This is the location of the original Historic Langston High School. Over the next 18 months we will be under construction on Silver Street in preparation of a grand opening of the facilities in March of 2019 and students and staff moving in to the building in the fall of 2019.





We are now putting the finishing touches on the new Hot Springs Junior Academy building which will be located on the east end of the High School current location. We hope to finalize these plans and have them to the state department by December 31. If our schedule stays true, then we are looking at beginning to work on the new junior academy in March of 2018.